Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the complianz-gdpr domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/stag_leaf/public_html/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the revisionary domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/stag_leaf/public_html/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the formidable domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/stag_leaf/public_html/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the all-in-one-wp-migration domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/stag_leaf/public_html/wp-includes/functions.php on line 6114
Modular Balconies Game Changer at Eastlands E05 - Sapphire Balconies
Contact

Modular Balconies Game Changer at Eastlands E05

Eastlands E05 is one phase of a substantial development of Wembley Park surrounding Wembley Stadium. Due to the project’s prominent location in the capital access to the site was strictly controlled with time slots for deliveries and minimal storage space. Sapphire’s offsite manufactured modular balconies were essential to maintaining the project programme and avoiding costly delays.

Wembley Park is an 85 acre development by Quintain comprising of an astounding 8,400 new homes, a 7 acre park and extensive office and retail space totalling 8.8 million sq ft. Wembley Park is set to be an exceptional place to live with bustling shops and venues and, of course, the stadium right on the doorstep.

Given the central location and proximity to the stadium, there was extremely limited storage space on site and strict security procedures for deliveries. The lack of space on site meant traditional balcony methods were not suitable and offsite production was essential.

Delivery timeslots had to be booked ahead of time for lorries to gain access to the holding area. This required precise timings for our logistics team and working closely with drivers and site to ensure deliveries ran smoothly. Thanks to the careful monitoring of lorries by our logistics team deliveries were well coordinated with the site team and other trades, ensuring the crane was available for installing the Glide-On™ balconies.

One of the ways the logistics and design team worked together to ensure smooth deliveries to site was by redesigning our double stacking trailers. Eastlands E05 required 444 balconies which were all the same size, meaning they could not be ‘nested’ together to reduce the number of loads. Instead, the double stacking trailer was carefully redesigned to allow for twice as many balconies to be transported per load while ensuring they remained safe and secure en route. This innovative solution not only met the logistical needs of E05 and other projects but also cut logistical costs and emissions in half.

Upon arrival, the balconies were immediately lifted from the lorries and installed directly on to the building for a quick and efficient install using our Remote Locking Device.

Eastlands E05 also featured precast panels from Techrete which included preinstalled windows. While precast panels bring a host of benefits, particularly for programme speeds, they also require consideration from the anchor design stage.

To guarantee the rigidity of the balconies and facilitate a quick install a unique socket stub was designed to be fitted between the precast panels. This meant the stubs had to be designed in close coordination with Techrete to an exact specification with strict quality control. In addition, the stubs were manufactured to be installed in line with the installation of the panels. As each panel was positioned and secured, the stubs would be installed into the awaiting slots before the next panel secured them in place.

The use of MMC at Eastlands E05, from modular balconies to precast panels, enabled the challenges of the site location to be overcome without compromising on quality or efficiency.