Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the complianz-gdpr domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/stag_leaf/public_html/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the revisionary domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/stag_leaf/public_html/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the formidable domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/stag_leaf/public_html/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the all-in-one-wp-migration domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/stag_leaf/public_html/wp-includes/functions.php on line 6114
Glide-On Cassette Balconies at Ash House, Staines - Sapphire Balconies
Contact

Ash House, Staines

Client:   ISG PLC

Contractor:   Comprehensive Design Architects

Location:   Staines

Balconies:   34 Cassettes® and 7 Juliet Balconies

Download full case study

Download

Challenge

Ash House was a regeneration project located in Staines-Upon-Thames, which saw an old office block converted into 41 residential apartments. Unlike a new build, it was not possible for brackets to be cast in because the slab and façade had already been completed. This project also included a very narrow balcony projection and anodised fascias and soffits.

Solution

Working with CDA Group, we used post-fixed brackets through the existing slab and specialist lifting equipment to ensure the safe handling and install of balconies. For the fascias and soffits, a special aluminium grade was used, giving more consistency for anodising.

Installation process

Step 1: Post-fixed brackets were fixed through the existing slab. These were the back filled with grout to ensure voids didn’t affect the structural performance.

Step 2: The balconies were manufactured at our production facility in Winchester, where they were stored until required at the Ash House site.

Step 3: As the balconies were relatively narrow, they were transported to site sitting in pairs side by side to minimise transport movements.

Step 4: Using specialist lifting equipment ensured safe handling of the final installation. A tree close to the building meant that the lifting operations were very tricky, so very long chains had to be used from the counterbalance.

Case Studies